Back to Practice Quantitative Aptitude

Time & Work - Practice MCQs for CCAT

60 Questions Section A: Fundamentals Quantitative Aptitude

Time & Work Question Bank for C-CAT

Topic-wise Time & Work MCQs for CDAC C-CAT preparation with answers and explanations.

Q1.
A can do a work in 10 days and B can do it in 15 days. In how many days can they do it together?
A5 days
B8 days
C6 days
D12 days
Show Answer & Explanation

Correct Answer: C - 6 days

Combined rate = 1/10 + 1/15 = 1/6. So time = 6 days.

Q2.
If 6 men can complete a work in 8 days, how many days will 4 men take?
A12 days
B10 days
C14 days
D16 days
Show Answer & Explanation

Correct Answer: A - 12 days

Work = 6×8 = 48 man-days. For 4 men: 48/4 = 12 days.

Q3.
A can do a work in 12 days. B is 50% more efficient than A. In how many days can B complete the work?
A6 days
B8 days
C9 days
D10 days
Show Answer & Explanation

Correct Answer: B - 8 days

B is 1.5 times efficient. B's time = 12/1.5 = 8 days.

Q4.
A does 40% of a work in 8 days. He then calls B and they complete the remaining work in 6 days. In how many days can B alone do the work?
A35 days
B30 days
C20 days
D40 days
Show Answer & Explanation

Correct Answer: C - 20 days

A completes 40% in 8 days, so A works at 5% per day. During the next 6 days, A completes 30% and B completes the remaining 30%. B also works at 5% per day, so B alone needs 20 days.

Q5.
A and B can do a work in 8 days. B and C can do it in 12 days. A and C can do it in 8 days. In how many days can A alone do the work?
A16 days
B12 days
C20 days
D24 days
Show Answer & Explanation

Correct Answer: B - 12 days

2(A+B+C) = 1/8+1/12+1/8 = 1/3. A+B+C = 1/6. A = 1/6-1/12 = 1/12. A = 12 days.

Q6.
A can complete a job in 20 days. A and B together complete it in 12 days. In how many days can B alone complete it?
A25 days
B35 days
C30 days
D40 days
Show Answer & Explanation

Correct Answer: C - 30 days

B's rate = 1/12 - 1/20 = (5-3)/60 = 1/30. B = 30 days.

Q7.
12 men can complete a work in 18 days. 6 days after they started, 4 more men joined. In how many more days will the work be completed?
A9 days
B8 days
C10 days
D12 days
Show Answer & Explanation

Correct Answer: A - 9 days

Total work = 12×18 = 216. Done in 6 days = 72. Remaining = 144. 16 men: 144/16 = 9 days.

Q8.
If 5 men or 8 women can do a work in 12 days, in how many days can 2 men and 3 women do it?
A15 days
B12 days
C18 days
D20 days
Show Answer & Explanation

Correct Answer: A - 15 days

5M = 8W, so 1M = 8/5 W. 2M+3W = 16/5+3 = 31/5 W. Time = (8×12)/(31/5) = 480/31 approx 15 days.

Q9.
A tap can fill a tank in 6 hours. After half the tank is filled, 3 more similar taps are opened. What is the total time to fill the tank?
A3 hrs 30 min
B4 hours
C3 hrs 45 min
D4 hrs 30 min
Show Answer & Explanation

Correct Answer: C - 3 hrs 45 min

Half tank in 3 hrs. Remaining half with 4 taps: (1/2)÷(4/6) = 3/4 hr = 45 min. Total = 3:45.

Q10.
A can do a piece of work in 4 hours. B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take?
A8 hours
B10 hours
C14 hours
D12 hours
Show Answer & Explanation

Correct Answer: D - 12 hours

A=1/4, B+C=1/3, A+C=1/2. C=1/2-1/4=1/4. B=1/3-1/4=1/12. B alone = 12 hours.

Q11.
A does a work in 10 days. B does it in 15 days. If they work on alternate days starting with A, in how many days will work be completed?
A11 days
B14 days
C13 days
D12 days
Show Answer & Explanation

Correct Answer: D - 12 days

In 2 days: 1/10+1/15 = 1/6. In 10 days: 5/6 done. Day 11: A does 1/10. Total = 5/6+1/10 = 14/15. Day 12: B finishes. Total = 12 days.

Q12.
Two pipes can fill a tank in 15 and 20 minutes. An outlet pipe can empty it in 30 minutes. With all three open, how long to fill?
A10 min
B12 min
C15 min
D18 min
Show Answer & Explanation

Correct Answer: B - 12 min

Net rate = 1/15 + 1/20 - 1/30 = (4+3-2)/60 = 5/60 = 1/12. Time = 12 min.

Q13.
A can complete work in 12 days working 8 hours a day. B can complete in 8 days working 10 hours a day. In how many days can they together complete working 8 hours a day?
A4 days
B5 days
C5.5 days
D6 days
Show Answer & Explanation

Correct Answer: C - 5.5 days

A requires 12*8 = 96 man-hours, and B requires 8*10 = 80 man-hours. Working together for 8 hours per day, their daily work is 8/96 + 8/80 = 1/12 + 1/10 = 11/60. Time required is 60/11, about 5.5 days.

Q14.
A alone can do 1/4 of the work in 2 days. B alone can do 1/3 of the work in 3 days. How many days for both together to complete?
A6 days
B5 days
C72/17 days
D8 days
Show Answer & Explanation

Correct Answer: C - 72/17 days

A completes the work in 8 days and B completes it in 9 days. Together their rate is 1/8 + 1/9 = 17/72, so the required time is 72/17 days.

Q15.
A can build a wall in 30 days. B can demolish it in 60 days. If A starts building and B joins after 15 days, when is wall complete?
A30 days
B45 days
C50 days
D60 days
Show Answer & Explanation

Correct Answer: B - 45 days

In 15 days, A builds 1/2. After that, A-B = 1/30-1/60 = 1/60 per day. Remaining 1/2 takes 30 days. Total = 45 days.

Q16.
10 men can complete work in 7 days. But 10 men start and 3 men leave after 2 days. In how many more days will work be completed?
A50/7 days
B7 days
C6 days
D9 days
Show Answer & Explanation

Correct Answer: A - 50/7 days

Total work is 10*7 = 70 man-days. The first 2 days complete 20 man-days, leaving 50 man-days. With 7 men remaining, the time required is 50/7 days.

Q17.
Wages for 45 women for 60 days are ₹81000. How many men must work 16 days to earn ₹13600 if daily wage ratio is 3:2?
A20
B35
C30
D25
Show Answer & Explanation

Correct Answer: D - 25

Woman wage/day = 81000/(45×60) = 30. Man wage/day = 45. Men needed: 13600/(45×16) = 18.89 ≈ 25.

Q18.
A work twice as fast as B. If B alone takes 30 days, in how many days can A and B together complete?
A8 days
B10 days
C12 days
D15 days
Show Answer & Explanation

Correct Answer: B - 10 days

A takes 15 days. Together: 1/15+1/30 = 3/30 = 1/10. Time = 10 days.

Q19.
A cistern has two pipes. One can fill it in 8 hours, other in 4 hours. With cistern full, both opened along with waste pipe. It empties in 20 hours. Waste pipe can empty in:
A2 hrs
B2.5 hrs
C3 hrs
D4 hrs
Show Answer & Explanation

Correct Answer: B - 2.5 hrs

Fill rate = 1/8+1/4 = 3/8. Net empty = -1/20. Waste = 3/8+1/20 = 17/40. Time = 40/17 ≈ 2.35 hrs ≈ 2.5 hrs.

Q20.
A is thrice as efficient as B. A takes 40 days less than B to do a job. In how many days can they together complete?
A12 days
B18 days
C15 days
D20 days
Show Answer & Explanation

Correct Answer: C - 15 days

Let B take 3x days, A takes x days. 3x-x=40, x=20. A=20, B=60. Together: 1/20+1/60=4/60=1/15. Time=15 days.

Q21.
A can do a piece of work in 12 days and B in 18 days. Together they finish it in:
A9 days
B8 days
C6 days
D7.2 days
Show Answer & Explanation

Correct Answer: D - 7.2 days

Combined rate = 1/12+1/18 = 5/36. Time = 36/5 = 7.2 days.

Q22.
If 15 men can do a work in 20 days, 10 men will do it in:
A25 days
B30 days
C35 days
D40 days
Show Answer & Explanation

Correct Answer: B - 30 days

Total work = 15×20 = 300 man-days. Time for 10 men = 300/10 = 30 days.

Q23.
A does half the work in 6 days. He finishes remaining with B in 2 days. B alone can do it in:
A6 days
B8 days
C12 days
D10 days
Show Answer & Explanation

Correct Answer: A - 6 days

A's rate = 1/12 per day. In 2 days, A does 2/12=1/6. B does 1/2-1/6=1/3 in 2 days. B's rate=1/6. B alone=6 days.

Q24.
A and B together can complete a task in 8 days. A alone takes 12 days. B alone takes:
A18 days
B20 days
C16 days
D24 days
Show Answer & Explanation

Correct Answer: D - 24 days

B's rate = 1/8 - 1/12 = 1/24. B alone = 24 days.

Q25.
10 men working 6 hours a day can finish a work in 14 days. 12 men working 7 hours a day will finish it in:
A12 days
B10 days
C8 days
D14 days
Show Answer & Explanation

Correct Answer: B - 10 days

Total = 10×6×14 = 840 man-hours. Time = 840/(12×7) = 10 days.

Q26.
A can do a work in 10 days. He works for 4 days. What fraction of work is left?
A1/2
B2/5
C3/5
D4/5
Show Answer & Explanation

Correct Answer: C - 3/5

Work done = 4/10 = 2/5. Left = 1-2/5 = 3/5.

Q27.
A is twice as fast as B. Together they finish in 12 days. A alone takes:
A24 days
B18 days
C16 days
D20 days
Show Answer & Explanation

Correct Answer: B - 18 days

A's rate=2x, B's rate=x. 3x=1/12. x=1/36. A's rate=2/36=1/18. A alone=18 days.

Q28.
A tap fills a tank in 6 hours and a drain empties it in 8 hours. If both are open, tank fills in:
A24 hours
B12 hours
C18 hours
D48 hours
Show Answer & Explanation

Correct Answer: A - 24 hours

Net rate = 1/6 - 1/8 = 1/24. Tank fills in 24 hours.

Q29.
3 men and 4 women can do a work in 6 days. 5 men and 2 women can do it in 4 days. 1 man and 1 woman can do it in:
A12 days
B15 days
C10 days
D56/3 days
Show Answer & Explanation

Correct Answer: D - 56/3 days

Let daily rates be M and W. 3M+4W=1/6 and 5M+2W=1/4. Solving gives M=1/21 and W=1/168, so M+W=3/56. Time = 56/3 days.

Q30.
A work is done by 30 workers in 20 days. After 12 days, 10 workers left. Remaining work is done in:
A10 days
B12 days
C8 days
D15 days
Show Answer & Explanation

Correct Answer: B - 12 days

Total=30×20=600. Done=30×12=360. Left=240. Workers=20. Days=240/20=12.

Q31.
If 5 machines produce 100 units in 4 hours, 8 machines produce 200 units in:
A5 hours
B4 hours
C6 hours
D8 hours
Show Answer & Explanation

Correct Answer: A - 5 hours

Rate per machine = 100/(5×4) = 5 units/hour. 8 machines = 40 units/hour. Time = 200/40 = 5 hours.

Q32.
A can complete 1/3 of work in 5 days. B can complete 2/5 of work in 10 days. Together they finish in:
A75/8 days
B10 days
C75/7 days
D12 days
Show Answer & Explanation

Correct Answer: A - 75/8 days

A completes the work in 15 days and B in 25 days. Together their rate is 1/15 + 1/25 = 8/75, so time = 75/8 days.

Q33.
A does a job in 18 days, B in 12 days. A starts alone and after 6 days B joins. Total time to complete:
A54/5 days
B12 days
C14 days
D11 days
Show Answer & Explanation

Correct Answer: A - 54/5 days

A does 6/18 = 1/3 of the job in 6 days. Remaining work is 2/3. Together A and B work at 1/18+1/12=5/36 per day, so remaining time is 24/5 days. Total time = 54/5 days.

Q34.
A pipe fills a cistern in 10 minutes. Another pipe can fill it in 15 minutes. Both opened together, cistern fills in:
A8 minutes
B5 minutes
C6 minutes
D12 minutes
Show Answer & Explanation

Correct Answer: C - 6 minutes

Combined = 1/10 + 1/15 = 5/30 = 1/6. Time = 6 minutes.

Q35.
A can do a piece of work in 40 days. He works at it for 8 days and then B finishes the remaining work in 16 days. B alone can do it in:
A24 days
B25 days
C30 days
D20 days
Show Answer & Explanation

Correct Answer: D - 20 days

A does 8/40=1/5. Remaining=4/5. B does 4/5 in 16 days. B alone=16×5/4=20 days.

Q36.
20 men can build a wall in 12 days. How many men needed to build it in 8 days?
A35
B25
C30
D28
Show Answer & Explanation

Correct Answer: C - 30

Men×Days = constant. 20×12 = M×8. M = 30.

Q37.
A is thrice as efficient as B. Together they finish work in 15 days. A alone finishes in:
A25 days
B18 days
C20 days
D15 days
Show Answer & Explanation

Correct Answer: C - 20 days

A=3x, B=x. 4x=1/15. x=1/60. A=3/60=1/20. A alone=20 days.

Q38.
Two pipes A and B fill a tank in 20 and 30 minutes. If both opened for 5 minutes, what fraction is filled?
A1/3
B5/12
C1/4
D7/12
Show Answer & Explanation

Correct Answer: B - 5/12

Rate = 1/20+1/30 = 5/60 = 1/12. In 5 min = 5/12.

Q39.
A completes 60% of a task in 9 days. He works 3 more days. Remaining work is done by B in 5 days. B alone finishes full task in:
A25 days
B20 days
C15 days
D30 days
Show Answer & Explanation

Correct Answer: A - 25 days

A's rate = 60%/9 = 20/3% per day. In 3 more days = 20%. Total by A = 80%. B does 20% in 5 days. B alone = 5×5 = 25 days.

Q40.
A father and son together paint a house in 6 days. Father alone takes 9 days. Son alone takes:
A20 days
B15 days
C12 days
D18 days
Show Answer & Explanation

Correct Answer: D - 18 days

Son's rate = 1/6 - 1/9 = 1/18. Son alone = 18 days.

Q41.
If 8 men can reap 40 hectares in 5 days, then 6 men can reap 60 hectares in:
A15 days
B8 days
C12 days
D10 days
Show Answer & Explanation

Correct Answer: D - 10 days

Rate = 40/(8×5) = 1 hectare per man per day. For 60 hectares with 6 men: 60/6 = 10 days.

Q42.
Efficiency of A is half of B. A can finish work in 24 days. Both together finish in:
A10 days
B8 days
C12 days
D6 days
Show Answer & Explanation

Correct Answer: B - 8 days

A's rate=1/24. B is twice efficient: rate=1/12. Together=1/24+1/12=3/24=1/8. Time=8 days.

Q43.
A, B, C can individually finish a work in 10, 12, 15 days. Working together, they finish in:
A6 days
B5 days
C4 days
D3 days
Show Answer & Explanation

Correct Answer: C - 4 days

1/10+1/12+1/15=6/60+5/60+4/60=15/60=1/4. Together=4 days.

Q44.
12 workers complete a project in 10 days working 8 hours/day. How many workers for 6 days, 10 hours/day?
A16
B14
C18
D20
Show Answer & Explanation

Correct Answer: A - 16

12×10×8 = W×6×10. W = 960/60 = 16.

Q45.
A leak empties a full tank in 12 hours. An inlet fills it in 8 hours. If tank is full and both work, it empties in:
A18 hours
B20 hours
C16 hours
D24 hours
Show Answer & Explanation

Correct Answer: D - 24 hours

Net rate = 1/12 - 1/8 = -1/24 (emptying). Time to empty = 24 hours.

Q46.
X works twice as fast as Y and thrice as fast as Z. Together they complete work in 10 days. X alone:
A15 days
B20 days
C18.33 days
D25 days
Show Answer & Explanation

Correct Answer: C - 18.33 days

X=6k, Y=3k, Z=2k. 11k=1/10. k=1/110. X=6/110=3/55. X alone=55/3≈18.33 days.

Q47.
30 men can complete a job in 12 days. After 4 days, 6 men leave. Remaining job takes:
A12 days
B10 days
C8 days
D14 days
Show Answer & Explanation

Correct Answer: B - 10 days

Total=360 man-days. Done=30×4=120. Left=240. Workers=24. Time=240/24=10 days.

Q48.
A works for 2 days and B for 3 days. Together they finish 1/4 of work. A works for 3 days and B for 6 days to finish 2/5. A alone finishes in:
A10 days
B15 days
C25 days
D30 days
Show Answer & Explanation

Correct Answer: A - 10 days

From 2A+3B=1/4 and 3A+6B=2/5. Doubling the first gives 4A+6B=1/2. Subtracting the second equation gives A=1/10, so A alone finishes in 10 days.

Q49.
If A can finish work in 10 days and B can finish 40% of same work in 4 days, together they finish it in:
A5 days
B6 days
C4 days
D7 days
Show Answer & Explanation

Correct Answer: A - 5 days

A rate=1/10. B does 40% in 4 days, so full in 10 days. B rate=1/10. Together=2/10=1/5. Time=5 days.

Q50.
A works 3 times faster than B. If B alone takes 24 days, how long do they take together?
A6 days
B8 days
C4 days
D12 days
Show Answer & Explanation

Correct Answer: A - 6 days

B rate=1/24. A rate=3/24=1/8. Together=1/24+1/8=4/24=1/6. Time=6 days.

Q51.
A can finish a work in 12 days and B in 18 days. Working together, they finish it in:
A6.5 days
B7.2 days
C8 days
D9 days
Show Answer & Explanation

Correct Answer: B - 7.2 days

Combined rate = 1/12 + 1/18 = 5/36. Time = 36/5 = 7.2 days.

Q52.
A is twice as efficient as B. Together they finish work in 10 days. A alone will take:
A12 days
B15 days
C20 days
D30 days
Show Answer & Explanation

Correct Answer: B - 15 days

Rates A:B = 2:1. Total 3 units finishes in 10 days. A alone time = 10 x 3/2 = 15 days.

Q53.
A and B can do work in 20 days, B and C in 30 days, C and A in 24 days. A alone takes:
A30 days
B36 days
C40 days
D48 days
Show Answer & Explanation

Correct Answer: C - 40 days

AB=1/20, BC=1/30, CA=1/24. Adding gives 2(A+B+C)=1/8. A=(AB+AC-BC)/2 = (1/20+1/24-1/30)/2=1/40.

Q54.
A pipe fills a tank in 15 hours and a leak empties it in 30 hours. Net fill time is:
A20 hours
B25 hours
C30 hours
D45 hours
Show Answer & Explanation

Correct Answer: C - 30 hours

Net rate = 1/15 - 1/30 = 1/30, so time is 30 hours.

Q55.
A can do a job in 16 days. After A works for 4 days, B completes remaining work in 9 days. B alone takes:
A10 days
B12 days
C14 days
D16 days
Show Answer & Explanation

Correct Answer: B - 12 days

A completes 4/16 = 1/4. Remaining 3/4 is done by B in 9 days, so B alone takes 12 days.

Q56.
12 men complete a work in 15 days. After 5 days, 4 men leave. Remaining work will finish in:
A12 days
B15 days
C18 days
D20 days
Show Answer & Explanation

Correct Answer: B - 15 days

Total work=180 man-days. Work done=60. Remaining=120. With 8 men, time=15 days.

Q57.
A, B, C can complete work in 10, 15, 30 days. If they work together, time taken is:
A4 days
B5 days
C6 days
D7 days
Show Answer & Explanation

Correct Answer: B - 5 days

Combined rate = 1/10+1/15+1/30 = 1/5, so time is 5 days.

Q58.
A works 50% faster than B. If B alone takes 30 days, together they take:
A10 days
B12 days
C15 days
D18 days
Show Answer & Explanation

Correct Answer: B - 12 days

B rate=1/30, A rate=1/20. Combined=1/12, so time=12 days.

Q59.
Two pipes fill a tank in 12 and 20 hours. A third pipe empties it in 30 hours. All open together take:
A8 hours
B10 hours
C12 hours
D15 hours
Show Answer & Explanation

Correct Answer: B - 10 hours

Net rate = 1/12+1/20-1/30 = 5/60+3/60-2/60 = 6/60 = 1/10.

Q60.
A contract needs 240 worker-days. If 16 workers work for 9 days, percent work left is:
A35%
B40%
C45%
D50%
Show Answer & Explanation

Correct Answer: B - 40%

Work done=144 worker-days. Remaining=96. Percent left=96/240 x 100 = 40%.

Showing 1-10 of 60 questions